Station 1 - Installing the size/decap die
Warning:
Never attempt to de-prime live primers, an explosion may result in serious injury or even
death.
To set up the toolhead you'll need to have empty brass,bullets, primers, powder and
a loading manual.
1. Raise the platform, by pulling the handle toward you and all the
way down.
2. Screw the sizing die into Station 1. Continue to screw the die down
until it just touches the shellplate. Tighten the die lockring finger tight Now
lower the platform by raising the handle to its upright position.
3. Place a case in the casefeed funnel. The case a should drop to the
casefeed arm bushing.
4. Raise the platform. The inserter cam pushes the feed arm bushing over
the body, dropping the case onto the Station 1 locator.
5. Lower the platform. The case is inserted into Station 1.
After raising the handle, insure that you push the handle away from you to it's
stop. Figure 28. This will insure that the case is fully inserted into
Station 1.
6. Again, raise the platform. The case is now sized. If the case
has a spent primer, it will be deprimed. Leave the platform in the raised position with
the case fully inserted in the die. This will ensure that the die remains in alignment
when tightening the lockring.
7. Using a 1-1/8" wrench to turn the lockring and a 7/8" wrench
to hold the die body, tighten the lockring Figure 29.
|
|
|